Solar Project

Final Evaluation Report

Energy Savings Improvement Project

The information listed below is the current status on the district’s Energy Project.

Schools Field Wiring Completed  Field Devices/
Control Panels Completed
Comm. Loop Completed/
Terminated
Walnut Ridge
Cedar Mountain
Glen Meadow
Rolling Hills
Lounsberry
High School
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
85%

The field wiring consists of wires that are run throughout the entire building going from every classroom to the main control boxes, which are located in our boiler rooms.

Field devices are computer boards that are connected to our existing HVAC units and chillers. The control panels are the boxes that are mounted inside each boiler room which holds all of the networking information which will span district-wide.

The comm. loop process is for the programmer engineer to check to make sure all of the systems are talking to the main system so we can operate our schools over the network.

Preliminary lighting schedule (number of fixtures per school, this does not include all of the occupancy controls in each classroom)

  • Walnut Ridge lighting (570) Completed
  • Glen Meadow lighting (990) and Cedar Mountain (1,005) Completed
  • Lounsberry lighting (1,200) and Rolling Hills (725) Completed
  • High School lighting (3,900) 65% completed

Please open power point to see the great progress we had during the summer months.  Click here to download. Please use your arrow keys to navigate the presentation.

Upcoming Events

June 2023

Monday June 12

9:45 am – 12:05 pm
Senior Walk
1:30 pm – 2:30 pm
LH SCA Meeting
4:00 pm – 5:00 pm
RHPS Gr. 2 Orientation (session 2)
5:30 pm – 7:00 pm
21st CCLC Family Night
6:00 pm – 7:30 pm
Tentative GATE Showcase @ CMPS
6:00 pm – 7:00 pm
VTSD GATE Showcase at GM
View the Full VTSD Calendar